Lahmont Bridge Builders built a bridge for the state of Maryland over a two-year period. The contracted

Question:

Lahmont Bridge Builders built a bridge for the state of Maryland over a two-year period. The contracted price for the bridge was $600,000. The costs incurred by Lahmont and the payments from the State of Maryland over the two-year period follow. Period 1 Period 2 Total Costs incurred by Lahmont $300,000 $100,000 $400,000 Payments from Maryland $400,000 $200,000 $600,000 168 Part 2 Use, Measurement, and Mechanics of Financial Statements REQUIRED:

a. Prepare income statements for Lahmont for the two periods under the following assump¬ tions: (1) Revenue is recognized at the end of the project. (2) Revenue is recognized in proportion to the costs incurred by Lahmont. (3) Revenue is recognized when the payments are received.

b. Calculate the total net income over the two-year period under each assumption.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: