10. In a two-machine sequencing problem, if the lowest times are both on the second machine and...
Question:
10. In a two-machine sequencing problem, if the lowest times are both on the second machine and they are tied for jobs, say 2 and 7, then the job 2 should be done in the end while job 7 in the first place.Mark the statement as T (True) or F (False).