18. A manufacturer receives an order from a state transport corporation for six buses, to be delivered

Question:

18. A manufacturer receives an order from a state transport corporation for six buses, to be delivered two at a time over the next three months. Production data for the manufacturer are shown in the following table:

image text in transcribed

Buses can be delivered to the city at the end of the same month in which they are assembled, or they can be stored by the manufacturer, at a cost of Rs 3,000 per bus per month for shipment during a later month. The manufacturer has no current inventory of these buses and desires none after the completion of this contract.
Formulate this problem as a linear programming problem to determine a production schedule that will meet the corporation demand at minimum cost to the manufacturer.