29. A company manufactures two kinds of machines, each requiring a different manufacturing technique. The deluxe machine
Question:
29. A company manufactures two kinds of machines, each requiring a different manufacturing technique.
The deluxe machine requires 18 hours of labour, 9 hours of testing, and Yields a profit of Rs 400. The standard machine requires 3 hours oflabour, 4 hours of testing, and Yields a profit of Rs 200. There are 800 hours oflabour and 600 hours of testing available each month. A marketing forecast has shown the monthly demand for the standard machine to be no more than 150. The management wants to know the numbers of each model to produce monthly that will maximise total profit. Formulate and solve this as a linear programming problem. (MBA, Delhi, November, 2003)