A cabinet manufacturing company is planning to introduce a new model of cabinets which requires the following

Question:

A cabinet manufacturing company is planning to introduce a new model of cabinets which requires the following tasks:

image text in transcribed

The wheels are mounted after they are prepared. The base cannot be attached until the sides are assembled and the wheels mounted. The top cannot be attached nor the brackets inserted until the sides are assembled.
The shelves are inserted after the brackets are installed. The back panel is attached after the base and top are attached. The doors are attached after the shelves are inserted and the top and base are attached. The unit is painted after the back and doors are attached.
(i) Identify the immediate predecessors of each task and draw the network.
(ii) Find the critical path (s), and list the critical activities.
(iii) Obtain the earliest and latest start and completion times of all the activities and their total, free and independent floats.

Step by Step Answer: