A commercial project results in 0.5 acre of new pavement and 0.4 acre of milled and resurfaced

Question:

A commercial project results in 0.5 acre of new pavement and 0.4 acre of milled and resurfaced existing pavement. Calculate the required TSS removal and peak water quality runoff for this project based on the NJDEP Stormwater Management Rules. Base your calculations for a 10-minute time of concentration and select an MTD to address the water quality requirements for the project.