A project has the following characteristics: (a) Draw a PERT network for this project. (b) Find the

Question:

A project has the following characteristics:

image text in transcribed

(a) Draw a PERT network for this project.

(b) Find the critical path and the project completion time

(c) Prepare an activity schedule showing the ES, EF, LS, LF, and slack for each activity.

(d) Will the critical path change if activity G takes 10 weeks instead of 5 weeks? If so, what will be the new critical path?