Calculate the required storage of a detention system to attenuate the peak water quality from 1.5 cfs

Question:

Calculate the required storage of a detention system to attenuate the peak water quality from 1.5 cfs to 0.5 cfs. Base your calculations on modified rational method for a storm of 30-minute duration and a time of concentration of 15 minutes. If 48 in. solid pipes are used to provide the storage, what would be the required length of the pipe?