Estimate the hourly production and unit cost of rock excavation by drilling and blasting. The rock is

Question:

Estimate the hourly production and unit cost of rock excavation by drilling and blasting. The rock is a limestone having a seismic velocity of 6000 ft/s (1830 m/s).

Trial blasting indicates that 31⁄2-in. (8.9-cm) holes drilled in an 8-ft (2.44-m) rectangular pattern will provide the desired fracturing. A hole depth of 20 ft

(6.1 m) yields an effective depth of 18 ft (5.5 m).

The average drilling rate is estimated to be 70 ft/h

(21.4 m/h).A powder factor of 1 lb/BCY (0.59 kg/BCM)

of ANFO will be used.image text in transcribed