Estimate the time required to load 500 cu yd (382 m3) of gravel from a stockpile into
Question:
Estimate the time required to load 500 cu yd (382 m3) of gravel from a stockpile into trucks using a clamshell having a heaped capacity of 0.75 cu yd (0.57 m3). Estimated cycle time is 20 s. Job efficiency is estimated to be 50 min/h.