You are given in Figure 12.18 the network corresponding to a project. The activities of the project
Question:
You are given in Figure 12.18 the network corresponding to a project. The activities of the project require manpower of similar type and the requirements, in terms of the number of men, are shown in parentheses next to the activity identification and timing (in days) for each. Determine how the activities of the project may be scheduled in order to have as smooth a requirement for the manpower as possible, without causing a delay in the project completion