Suppose that management of Valley Cinemas would like to investigate the potential of using a scheduling system
Question:
The overall viewing schedule for the theater is composed of the individual schedules for each of the six movies. For each movie, a schedule must be developed that specifies the week the movie starts and the number of consecutive weeks it will run. For instance, one possible schedule for movie 2 is for it to start in week 1 and run for two weeks. Theater policy requires that once a movie is started, it must be shown in consecutive weeks. It cannot be stopped and restarted again. To represent the schedule possibilities for each movie, the following decision variables were developed:
For example, x532 = 1 means that the schedule selected for movie = is to begin in week 3 and run for two weeks. For each movie, a separate variable is given for each possible schedule. a. Three schedules are associated with movie 1. List the variables that represent these schedules.
b. Write a constraint requiring that only one schedule be selected for movie 1.
c. Write a constraint requiring that only one schedule be selected for movie 5.
d. What restricts the number of movies that can be shown in week 1? Write a constraint that restricts the number of movies selected for viewing in week 1.
e. Write a constraint that restricts the number of movies selected for viewing in week 3.
Step by Step Answer:
Essentials Of Business Analytics
ISBN: 611
1st Edition
Authors: Jeffrey Camm, James Cochran, Michael Fry, Jeffrey Ohlmann, David Anderson, Dennis Sweeney, Thomas Williams