Suppose we have five jobs with specified required times and deadlines: t1 = 25, d1 = 50;

Question:

Suppose we have five jobs with specified required times and deadlines: t1 = 25, d1 = 50; t2 = 15, d2 = 60; t3 = 20, d3 = 60; t4 = 5, d4 = 55; t5 = 10, d5 = 75. Find the maximum lateness of any job when the jobs are scheduled in this order (and they start at time 0): Job 3, Job 1, Job 4, Job 2, Job 5. Answer the same question for the schedule Job 5, Job 4, Job 3, Job 1, Job 2.