Sutton Construction Inc. is a privately held, family-founded corporation that builds single- and multiple-unit housing. Most projects Sutton Construction undertakes involve the construction of multiple
Answered step by step
Verified Expert Solution
Question
Sutton Construction Inc. is a privately held, family-founded corporation that builds single- and multiple-unit housing. Most projects Sutton Construction undertakes involve the construction of multiple units. Sutton Construction has adopted a job-order costing system for determining the cost of each unit. The costing system is fully computerized. Each project’s costs are divided into the following five categories:
69 users unlocked this solution today!
1. General conditions, including construction site utilities, project insurance permits and licenses, architect’s fees, decorating, field office salaries, and cleanup costs.
2. Hard costs, such as subcontractors, direct materials, and direct labor.
3. Finance costs, including title and recording fees, inspection fees, and taxes and discounts on mortgages.
4. Land costs, which refer to the purchase price of the construction site.
5. Marketing costs, such as advertising, sales commissions, and appraisal fees.
Recently, Sutton Construction purchased land for the purpose of developing 20 new single- family houses. The cost of the land was $250,000. Lot sizes vary from ¼ to ½ acre. The 20 lots occupy a total of eight acres.
General conditions costs for the project totaled $120,000. This $120,000 is common to all 20 units that were constructed on the building site.
Job3, the third house built in the project, occupied a ¼-acre lot and had the following hard costs:
Direct materials .....$ 8,000
Direct labor...... 6,000
Subcontractor ..... 14,000
For Job 3, finance costs totaled $4,765 and marketing costs, $800. General conditions costs are allocated on the basis of units produced. Each unit’s selling price is determined by adding 40 percent to the total of all costs.
Required:
1. Identify all production costs that are directly traceable to Job 3. Are all remaining production costs equivalent to overhead found in a manufacturing firm? Are there nonproduction costs that are directly traceable to the housing unit? Which ones?
2. Develop a job-order cost sheet for Job 3. What is the cost of building this house? Did you include finance and marketing costs in computing the unit cost? Why or why not? How did you determine the cost of land for Job 3?
3. Which of the five cost categories corresponds to overhead? Do you agree with the way in which this cost is allocated to individual housing units? Can you suggest a different allocation method?
4. Calculate the selling price of Job 3. Calculate the profit made on the sale of this unit.
Step by Step Solution
★★★★★
3.55 Rating (173 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1
1 Land 7813 Direct Materials 8000 Direct labor 6000 Subcontractor 14000 35813 2500008 31250 per acre 31250 025 7813 General condition costs and financ... View full answer

Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
100% Satisfaction Guaranteed-or Get a Refund!
Step: 2Unlock detailed examples and clear explanations to master concepts

Step: 3Unlock to practice, ask and learn with real-world examples

Document Format ( 1 attachment)

493-B-C-A-P-C (291).docx
120 KBs Word File
See step-by-step solutions with expert insights and AI powered tools for academic success
-
Access 30 Million+ textbook solutions.
-
Ask unlimited questions from AI Tutors.
-
Order free textbooks.
-
100% Satisfaction Guaranteed-or Get a Refund!
Claim Your Hoodie Now!

Study Smart with AI Flashcards
Access a vast library of flashcards, create your own, and experience a game-changing transformation in how you learn and retain knowledge
Explore Flashcards