Table 8.16 shows the activities, durations, and precedence relationships for a project. a. Construct an activity on

Question:

Table 8.16 shows the activities, durations, and precedence relationships for a project.
Table 8.16 shows the activities, durations, and precedence relationships for

a. Construct an activity on node (AON) network for this project.
b. Calculate the length of each project path and find how long it will take to complete the project.
c. Identify the project critical path and critical activities.