The calculations in PERT allow you to determine the probability that as project will be completed. Suppose

Question:

The calculations in PERT allow you to determine the probability that as project will be completed. Suppose you calculate that the probability a project will be completed by a target deadline is only 0.25. What steps might you take if you were the project manager? Would your decisions be different if the probability was calculated as 0.75? Would you be willing to take a 25% risk of failing to complete the project on time?
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

OM operations management

ISBN: 978-1285451374

5th edition

Authors: David Alan Collier, James R. Evans

Question Posted: