The City of Stockholm authorized construction of a $600,000 addition to the municipal building in September 2014.
Question:
REQUIRED:
Prepare journal entries for the capital projects fund and any other fund involved to the extent of requiring journal entries to record the transactions described.
1. On October 1, 2014, the general fund transferred $200,000 to the capital projects fund.
2. On November 1, 2014, a contract for the addition was awarded to Crooked Construction for $580,000.
3. On April 15, 2015, the $400,000, 7 percent bonds were sold for $401,000 and the premium was transferred to the debt service fund.
4. On May 2, 2015, construction was completed and Crooked Construction submitted a bill for $580,000.
5. On May 12, 2015, the bill to Crooked Construction was paid in full. The CPF was closed, and the remaining cash was transferred to the general fund.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Advanced Accounting
ISBN: 978-0133451863
12th edition
Authors: Floyd A. Beams, Joseph H. Anthony, Bruce Bettinghaus, Kenneth Smith
Question Posted: