Question: The CNC grinding section has a large number of machines devoted to grinding shafts for the automotive industry. The grinding machine cycle takes 3.6 min.

The CNC grinding section has a large number of machines devoted to grinding shafts for the automotive industry. The grinding machine cycle takes 3.6 min. At the end of this cycle an operator must be present to unload and load parts, which takes 40 sec.
(a) Determine how many grinding machines the worker can service if it takes 20 sec to walk between the machines and no machine idle time is allowed.
(b) How many seconds during the work cycle is the worker idle?
(c) What is the hourly production rate of this machine cluster?

Step by Step Solution

3.40 Rating (175 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a n 25660 427 Use n 1 4 grindi... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

795-C-S-A-I (651).docx

120 KBs Word File

Students Have Also Explored These Related Artificial Intelligence Questions!