The company signed a $1,450,000 contract to build an environmentally friendly access trail to Stansbury Peak. The
Question:
The company signed a $1,450,000 contract to build an environmentally friendly access trail to Stansbury Peak. The project was expected to take approximately three years. The following information was collected for each year of the project-Year 1, Year 2, and Year 3:
CostExpected
ExpendedAdditional
duringCost to
the YearCompletion
Year 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $200,000 . . . . . . . . . . $1,150,000
Year 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 350,000 . . . . . . . . . . ...1,020,000
Year 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 915,000 . . . . . . . . . . . . . . . . . . . 0
The company uses the percentage-of-completion method of computing revenue from long-term construction contracts, and the company employs the cost-to-cost method to estimate the percentage of completion. Make the journal entries to record revenue and cost for the construction project in
(1) Year 1,
(2) Year 2,
(3) Year 3.
Step by Step Answer: