Question: The Custom Bike Company has set up a weighted scoring matrix for evaluation of potential projects. Below are three projects under consideration. a. Using the
The Custom Bike Company has set up a weighted scoring matrix for evaluation of potential projects. Below are three projects under consideration.
a. Using the scoring matrix below, which project would you rate highest? Lowest?
b. If the weight for Strong Sponsor is changed from 2.0 to 5.0, will the project selection change? What are the three highest weighted project scores with this new weight?
c. Why is it important that the weights mirror critical strategicfactors?
.png)
Project Screening Matrix 2.0 5.0 4.0 3.0 1.03.0 Project 9 Project 2 3 Project 36 Project 41 Project5 3 10 101 7 2 0 5 0 5 10 69
Step by Step Solution
3.41 Rating (154 Votes )
There are 3 Steps involved in it
a Rate Project 5 the highest and Project 2 the lowest b Yes The three highest are Project... View full answer