The following data have been collected for a British health care IT project for two-week reporting periods
Question:
The following data have been collected for a British health care IT project for two-week reporting periods 2 through 12. Compute the SV, CV, SPI, and CPI for each period. Plot the EV and the AC on the summary graph provided. Plot the SPI, CPI, and PCIB on the index graph provided. What is your assessment of the project at the end of period12?