The following figure shows the bill of material (BOM) for the Acme PolyBob, a product that has proven unsuccessful in capturing roadrunners. Complete the MRP records. All the information you need is shown in the BOM and on the MRP records.

Item E: Lead time = 4 weeks; Minimum order quantity 5,000 WEEK 2 3 4 5 Gross requirements Scheduled receipts Projected ending inventory: 5,750 Net requirements Planned receipts Planned orders Item F: Lead time = 5 weeks; Minimum order quantity = 750 WEEK 3 4 Gross requirements Scheduled receipts Projected