a. Fee paid to attorney for title search . . . . . . . . . . . . . . . . . . . . . . . . . . $ 3,000
b. Cost of real estate acquired as a plant site: Land . . . . . . . . . . . . . . . . 325,000
Building . . . . . . . . . . . . . 75,000
c. Delinquent real estate taxes on property, assumed by purchaser . . . . 10,000
d. Special assessment paid to city for extension of water
main to the property . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12,800
e. Cost of razing and removing building . . . . . . . . . . . . . . . . . . . . . . . . 3,900
f. Proceeds from sale of salvage materials from old building . . . . . . . . 4,000*
g. Cost of filling and grading land . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17,500
h. Architect's and engineer's fees for plans and supervision . . . . . . . . . 40,000
i. Premium on one-year insurance policy during construction . . . . . . . . 4,800
j. Cost of trees and shrubbery planted . . . . . . . . . . . . . . . . . . . . . . . . . . 9,000
k. Money borrowed to pay building contractor . . . . . . . . . . . . . . . . . . . 800,000*
l. Cost of paving parking lot to be used by customers . . . . . . . . . . . . . . 15,000
m. Cost of repairing windstorm damage during construction . . . . . . . . 2,000
n. Cost of repairing vandalism damage during construction . . . . . . . . . . $ 2,500
o. Cost of floodlights installed on parking lot . . . . . . . . . . . . . . . . . . . . . 1,100
p. Interest incurred on building loan during construction . . . . . . . . . . . . 42,000
q. Payment to building contractor for new building . . . . . . . . . . . . . . . . 915,000
r. Proceeds from insurance company for windstorm and
vandalism damage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4,000*
s. Refund of premium on insurance policy (i) canceled after
11 months . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 400*
Instructions
1. Assign each payment and receipt to Land (unlimited life), Land Improvements (limited life), Building, or Other Accounts. Indicate receipts by an asterisk. Identify each item by letter and list the amounts in columnar form, as follows:
2. Determine the amount debited to Land, Land Improvements, and Building.
3. The costs assigned to the land, which is used as a plant site, will not be depreciated, while the costs assigned to land improvements will be depreciated. Explain this seemingly contradictory application of the concept ofdepreciation.
Step by Step Answer: