The following problem requires an understanding of the WBS, the cost account elements, and cost control analysis.
Question:
Which of the following is the value of WBS element 4.0?
a. $60.0
b. $30.0
c. $24.0
d. $54.0
Using the data in Figure, and the actual costs given below for WBS elements 5.1 through 5.4 and elements 4.1 and 4.2, answer the questions shown below:
Actual Costs
E-15.1 ........$1.0
E-15.3 ........$1.5
E-25.2 ........$1.0
E-25.4 ........$2.0
E-35.1 ........$1.0
E-35.3 ........$2.5
E-45.3 ........$3.0
E-45.2 ........$3.5
WBS element 5.1 ........$____
WBS element 5.2 ........$____
WBS element 5.3 ........$____
WBS element 5.4 ........$____
WBS element 4.1 ........$____
WBS element 4.2 ........$____
Functional element E-1 .....$____
Functional element E-2 .....$____
Functional element E-3 .....$____
Functional element E-4 .....$____
Functional element D-1 .....$____
Functional element D-2.....$____