The following table contains information concerning four jobs that are awaiting processing at a work center. a.

Question:

The following table contains information concerning four jobs that are awaiting processing at a work center.

The following table contains information concerning four jobs that are

a. Sequence the jobs using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. Assume the list is by order of arrival.
b. For each of the methods in part a, determine (1) the average job flow time, (2) the average tardiness, and (3) the average number of jobs at the work center.
c. Is one method superior to the others?Explain.