The following table contains the activities for planning a wedding and the activity time estimates; however, the

Question:

The following table contains the activities for planning a wedding and the activity time estimates; however, the precedence relationships between activities are not included:

The following table contains the activities for planning a wedding


Using your best judgment, determine the project network, critical path, and expected project duration. If it is January 1 and a couple is planning a June 1 wedding, what is the probability that it can be done on time?