The following table contains the activities for planning a wedding and the activity time estimates. However, the

Question:

The following table contains the activities for planning a wedding and the activity time estimates. However, the precedence relationships between activities are not included.

The following table contains the activities for planning a weddi

Using your best judgment, determine the project network, critical path, and expected project duration. If it is the first of January and a couple is planning a June 1 wedding, what is the probability that it can be done ontime?