Question: The government is planning a multiple-purpose hydroelectric project for a river basin. The estimated benefits and costs that are expected to be derived from the

The government is planning a multiple-purpose hydroelectric project for a river basin. The estimated benefits and costs that are expected to be derived from the three alternatives under consideration are as follows:
The interest rate is 8% and the life of each project is 40 years.
a. Using benefit-cost analysis, determine which project should be selected.
b. What is the rank-ordering of projects from best to worst?
c. If the projects involved intangible benefits that required considerable judgment in assigning their values, would your recommendation be affected?

The government is planning a multiple-purpose hydroelectric project for a

Initial Cost Annual benefits and costs $30,000,000 $40,000,000 $50,000,000 $1,600,000 $1,250,000 1,800,000 Power sales Flood control saving 225,000 $300,000 $500,000 Irrigation benefits $8,000,000 $450,000 $600,000 Recreation benefits $525,000 $150,000 $350,000 Operating and maintenance costs $220,000 $230,000 $350,000

Step by Step Solution

3.41 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Figures are in thousands Projects BC and E are accept... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

929-B-F-R-A (1012).docx

120 KBs Word File

Students Have Also Explored These Related Finance Questions!