The JX Company produces a touch -phone product form two end panels, three covers, and one pack.

Question:

The JX Company produces a touch -phone product form two end panels, three covers, and one pack. The end panels, covers, and packs have the following data and each requires a step:
End panel Run time Machine Setup time 2.0 hr. Operation 1 Saw 6 min. 2 Planer 12 min. 0.5 hr. Router Sander 1.0 hr. 3 15

The touch-phone product master schedule for the next four weeks is 100, 80, 120, and 200 units, respectively. There is a set up for each MPS quantity. What is the total number of hours required on each of the five machine centers for this four-week master schedule? (Each machine need to setup only 1 time per week)