The Manchester United Soccer Tournament project team has identified the following potential risks to their project: a.

Question:

The Manchester United Soccer Tournament project team has identified the following potential risks to their project:
a. Referees failing to show up at designated games.
b. Fighting between teams.
c. Pivotal error committed by a referee that determines the outcome of a game.
d. Abusive behavior along the sidelines by parents.
e. Inadequate parking.
f. Not enough teams sign up for different age brackets.
g. Serious injury.
How would you recommend that they respond (i.e., avoid, accept . . .) to these risks and why?