The new director of special events at a large university has decided to completely revamp graduation ceremonies.

Question:

The new director of special events at a large university has decided to completely revamp graduation ceremonies. Toward that end, a PERT chart of the major activities has been developed. The chart has five paths with expected completion times and variances as shown in the table. Graduation day is 16 weeks from now. Assuming the project begins now, what is the probability that the project will be completed before

The new director of special events at a large university

a. Graduation time?
b. The end of week 15?
c. The end of week13?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 978-0078024108

12th edition

Authors: William J Stevenson

Question Posted: