The number of abnormal spoiled units is 300 and the cost per equivalent unit is $2 for

Question:

The number of abnormal spoiled units is 300 and the cost per equivalent unit is $2 for materials and $3 for conversion. The inspection point is at the end of processing. There are 600 units in ending work-in-process and 200 normal spoiled units. What is the cost of spoilage shown separately on the cost report?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer: