The Pierson Construction Corporation contracted with the City of Plaquemine to construct a dam on the bayou

Question:

The Pierson Construction Corporation contracted with the City of Plaquemine to construct a dam on the bayou at a price of $14,000,000. Pierson expects to earn $1,270,000 on the contract. The percentage-of-completion method is to be used, and the completion stage is to be determined by estimates made by the engineer. The following schedule summarizes the activities of the contract for the years 2010–2012.


The Pierson Construction Corporation contracted with the City of


Instructions:
1. Prepare a schedule showing the revenue, cost, and the gross profit earned each year under the percentage-of-completion method, using the engineer's estimate as the measure of completion to be applied to revenues and costs.
2. Prepare all journal entries required to reflect the contract.
3. Prepare journal entries for 2012, assuming the completed-contract method is used.
4. How would the journal entries in (2) differ if the actual costs incurred were used to estimate the percentage completed for the period instead of the engineer'sestimate?

Corporation
A Corporation is a legal form of business that is separate from its owner. In other words, a corporation is a business or organization formed by a group of people, and its right and liabilities separate from those of the individuals involved. It may...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Intermediate Accounting

ISBN: 978-0324592375

17th Edition

Authors: James D. Stice, Earl K. Stice, Fred Skousen

Question Posted: