The planning department of an electronics firm has set up the activities for developing and production of

Question:

The planning department of an electronics firm has set up the activities for developing and production of a new phone. Given the information below, develop a project network using Microsoft Project. Assume a five-day workweek and the project starts on January 4, 2017.
Activity Description Activity Activity Time (weeks) ID Predecessor Staff None 2 2 Develop market program 3 Select channe

The project team has requested that you create a network for the project, and determine
if the project can be completed in 45 weeks.