The primary control loop of a nuclear power plant includes a time delay due to the need
Question:
The transfer function of the reactor and time delay is
where T = 0.4 s and T = 0.2 s. Using frequency response methods, design the controller so that the overshoot of the system is P.O. ¤ 10%. With this controller in the loop, estimate the percent overshoot and settling time (with a 2% criterion) to a unit step. Determine the actual overshoot and settling time and compare with the estimated values.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: