Question: The product development group at Landon Corporation has been working on a new computer software product that has the potential to capture a large market
The product development group at Landon Corporation has been working on a new computer software product that has the potential to capture a large market share. Through outside sources, Landon’s management learned that a competitor is working to introduce a similar product. As a result, Landon’s top management increased its pressure on the product development group. The group’s leader turned to PERT/CPM as an aid to scheduling the activities remaining before the new product can be brought to the market. The project network is as follows:
-1.png)
The activity time estimates (in weeks) are as follows:
-2.png)
a. Develop an activity schedule for this project and identify the critical path activities.
b. What is the probability that the project will be completed so that Landon Corporation may introduce the new product within 25 weeks? Within 30weeks?
Finish Start 0000055000 5764427366 0500050050 4353086625 m 0000055000 3342674524 tiv ABCDEFGHI
Step by Step Solution
3.40 Rating (162 Votes )
There are 3 Steps involved in it
a Activity Expected Time Variance A 4 011 B 4 044 C 5 011 D 3 011 E 10 178 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
148-M-S-Q-M (49).docx
120 KBs Word File