The project described in the following table is scheduled to be completed in 11 weeks. Construct a

Question:

The project described in the following table is scheduled to be completed in 11 weeks. Construct a network diagram using AOA or AON (see Example 5 for either type). Then answer the following questions:

The project described in the following table is scheduled to

a. If you were the manager of this project, would you be concerned? Explain.
b. If there is a penalty of $ 5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000?