The project referred to in Problem 28 has been partially completed. Task a required four weeks, task

Question:

The project referred to in Problem 28 has been partially completed. Task a required four weeks, task b nine weeks, task c four weeks, and task d five weeks. Update the simulation model you developed for Problem 28 and calculate the probability that the project will be finished in 23 weeks. Explain why the probability of completing the project in 23 weeks has changed.