The standard cost of product 2525 includes 1.9 hours of direct labour at $14.00 per hour. The
Question:
The standard cost of product 2525 includes 1.9 hours of direct labour at $14.00 per hour. The predetermined overhead rate is $22.00 per direct labour hour. During July, the company incurred 4,100 hours of direct labour at an average rate of $14.30 per hour and $81,300 of manufacturing overhead costs. It produced 2,000 units.
Instructions
(a) Calculate the total, price, and quantity variances for labour.
(b) Calculate the total overhead variance.