The Texas Consolidated Electronics Company is contemplating a research and development program encompassing eight research projects. The
Question:
The Texas Consolidated Electronics Company is contemplating a research and development program encompassing eight research projects. The company is constrained from embarking on all projects by the number of available management scientists (40) and the budget available for R&D projects ($300,000). Further, if project 2 is selected, project 5 must also be selected (but not vice versa). Following are the resource requirements and the estimated profit for each project:
1. Define the decision variables
2. Develop the objective function
3 Write the constraints
4 Solve the problem in Excel