The three-station work cell at Pullman Mfg., Inc. is illustrated in figure S7.8. It has two machines
Question:
(a) What is the process cycle time of this work cell?
(b) What is the system process time of this work cell?
(c) If the firm operates 8 hours per day, 6 days per week, what is the weekly capacity of this workcell?