Question:
The Valley United Soccer Club is planning a soccer tournament for the weekend of April 2930. The clubs officers know that by March 30 they must send out acceptances to teams that have applied to enter and by April 15 they must send out the tournament game schedule to teams that have been selected to play. Their tentative plan is to begin the initial activities for tournament preparation including sending out the application forms to prospective teams, on January 20. Following is a list of tournament activities, their precedence relationships, and estimates of their duration in days. Develop a project network for the clubs tournament preparation process and determine the likelihood that they will meet their schedule milestones and complete the process according to the scheduled tournament start date of April29.
Transcribed Image Text:
Time Estimates Activity(days) Activity Activity Description a Send application forms b Get volunteer workers C Line up referees d Reserve fields e Receive and process forms f Determine age divisions Predecessor a m b 5 7 10 10 18 26 7 10 14 14 21 35 30 30 30 b, c, d,e 4 9 12 g Assign fields to dvisions h Sell program ads 14 21 30 15 20 26 iAcqire donated items for team gift bags j Schedule games k Design ads LFill gift bags m Process team t-shirt orders n Send acceptance letters 0 p Put together registration 6 14 18 5 8 10 9 12 17 7 10 14 4 7 12 Design and print programsj,k, Ln 14 18 24 boxes (programs, gifts, etc.) q Send out game schedules j,k,ln 5 8 12 r Assign referees to gamesjk,Ln 4 7 10 s Get trophies t Silk-screen t-shirts u Package team t-shirt orders 20 28 35 12 17 25 5 8 12