Transmissions are delivered to the fabrication line four at a time. It takes one hour for transmissions

Question:

Transmissions are delivered to the fabrication line four at a time. It takes one hour for transmissions to be delivered. Approximately four vehicles are produced each hour, and management has decided that 50 percent of expected demand should be maintained as safety stock. How many kanban card sets are needed?