Triangle Utilities provides electricity for three cities. The company has four electric generators that are used to

Question:

Triangle Utilities provides electricity for three cities. The company has four electric generators that are used to provide electricity. The main generator operates 24 hours per day, with an occasional shutdown for routine maintenance. Three other generators (1, 2, and 3) are available to provide additional power when needed. A startup cost is incurred each time one of these generators is started. The startup costs are $6,000 for 1, $5,000 for 2, and $4,000 for 3. These generators are used in the following ways: A generator may be started at 6:00 A.M. and run for either 8 hours or 16 hours, or it may be started at 2:00 P.M. and run for 8 hours (until 10:00 P.M.). All generators except the main generator are shut down at 10:00 P.M. Forecasts indicate the need for 3,200 megawatts more than provided by the main generator before 2:00 P.M., and this need goes up to 5,700 megawatts between 2:00 and 10:00 P.M. Generator 1 may provide up to 2,400 megawatts, generator 2 may provide up to 2,100 megawatts, and generator 3 may provide up to 3,300 megawatts. The cost per megawatt used per eight hour period is $8 for 1, $9 for 2, and $7 for 3.

(a) Formulate this problem as an integer programming problem to determine the least-cost way to meet the needs of the area.

(b) Solve using computer software.


Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Analysis For Management

ISBN: 162

11th Edition

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

Question Posted: