Use the following activities and their three duration estimates (in days) to do the following: a. Determine

Question:

Use the following activities and their three duration estimates (in days) to do the following:
a. Determine the expected duration of the project.
b. Calculate the probability' that the project will take at least 18 days.
Use the following activities and their three duration estimates (in