Use the information contained below to compress one time unit per move using the least cost method.

Question:

Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost.

Normal Normal Maximum Crash Cost (Slope) Crash Time Time Act. Cost A 100 150 B 80 3 100 60 2 200 D 40 200 40 5 200 40 15
3 Project duration 16 3 A 1x 2 5 E Total direct cost 1,400 5