Using the figure in question 11, perform resource-limited scheduling. Assume that you have only three workers available

Question:

Using the figure in question 11, perform resource-limited scheduling. Assume that you have only three workers available at any given time. What is the new completion date for the project?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Successful Project Management

ISBN: 9780324656138

4th Edition

Authors: Jack Gido, Jim Clements

Question Posted: