Using the following project information The critical path is A-C-E-G-I-J. (a) Calculate the probability that the project

Question:

Using the following project information
Optimistic Time Expected Activity Most Pessimistic Immediate Variance Likely Predecessor(s) Estimate(weeks) Time Time Ti

The critical path is A-C-E-G-I-J.
(a) Calculate the probability that the project will be completed in 38 weeks.
P(project 38) =
(b) Calculate the probability that the project will be completed in 42 weeks.
P(project 42) =

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Methods of IT Project Management

ISBN: 978-1557536631

2nd edition

Authors: Jeffrey Brewer, Kevin Dittman

Question Posted: