Using the information below, draw an AOA network. Find the critical path and use it to compute

Question:

Using the information below, draw an AOA network. Find the critical path and use it to compute the number of days you would be 95 percent sure the project would be completed. Calculate the slack, earliest start, and latest start times for each activity and show in table form. Does any path come close to causing a problem in determining the probability of project completion based on the critical path alone?
Using the information below, draw an AOA network. Find the
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management A Managerial Approach

ISBN: 978-0470226216

7th Edition

Authors: Jack R. Meredith, Samuel J. Mantel,

Question Posted: