Using the network above and the additional information below, find: (a) The crash cost per day (b)

Question:

Using the network above and the additional information below, find:

(a) The crash cost per day

(b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost. Assume partial crashing isallowed.

Using the network above and the additional information below, fi
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management A Managerial Approach

ISBN: 978-0470226216

7th Edition

Authors: Jack R. Meredith, Samuel J. Mantel,

Question Posted: